End in sight for the Royal Navy’s Type 23 frigate LIFEX programme
Here we provide an update on the complex support programme that is being undertaken to keep the Type 23 frigates in service.
The programme of life extension refits to upgrade and repair the ageing Type 23 frigates to serve beyond their 30th birthdays is almost complete. The last ship to undergo this process, HMS Sutherland is still in the Frigate Support Centre (FSC) shed at Devonport but will undock in late February and should be ready to be handed back to the RN in June.
Each frigate undergoing life extension (LIFEX) refit has a hull survey and repairs, the Sea Wolf missile system replaced with Sea Ceptor, new Artisan radar (if not already fitted) and a wide range of other upgrades and refurbishments. While delivering an important capability boost, the work has mostly taken longer than expected and the work on each vessel has often been a unique project. As each ship was stripped down and surveyed, different levels of hull corrosion, structural problems and equipment deterioration were revealed. This partly explains why the time taken for each ship has varied significantly between vessels.
Frigate* | PGMU status | LIFEX refit start | LIFEX refit end | LIFEX duration (months) | First post-LIFEX refit start |
HMS Westminster | N | Oct 2014 | Mar 2017 | 30 | To be decommissioned |
HMS Argyll | N | May 2015 | Apr 2017 | 24 | May 2022 |
HMS Montrose | N | Mar 2014 | July 2015 | 17 | Decommissioned |
HMS Northumberland | Future? | May 2016 | Apr 2018 | 23 | Due Mar 2024 |
HMS Kent | Future? | Oct 2016 | Oct 2018 | 25 | Due June 2024 |
HMS Lancaster | N | May 2017 | Mar 2020 | 36 | |
HMS Richmond | Y | Sept 2017 | Mar 2020 | 30 | |
HMS Portland | Future? | Apr 2018 | May 2021 | 37 | First to have new S2150 Bow Mounted Sonar |
HMS Somerset | Future? | Oct 2018 | May 2022 | 43 | Post-refit issues delayed return to service until late 2023 |
HMS Iron Duke | N | May 2019 | Jun 2023 | 49 | |
HMS St Albans | Y | Mid 2019 | Mar 2024 | 58 | |
HMS Sutherland | Y | Dec 2020 | Jun 2024 | 42 |
The original cost estimate for each LIFEX project was around £35M (excluding the engine upgrades) but this has been exceeded in most cases. HMS Iron Duke was the most extreme example, She did not receive new engines and required 2,000 steel inserts to make her seaworthy in a package that eventually cost £103M. The official figure for HMS Somerset was £60.7M, although she continued to suffer from defects well after the refit was complete. The cost of the LIFEX for every ship has not been released into the public domain, with the MoD citing “commercial sensitivity”.
The impacts of the pandemic clearly did not help but progress was slower than expected. Against expectation, the trend has been that LIFEX projects are taking longer for the later ships. Babcock says they have never delivered a ship late back to the customer and work with the RN to coordinate handover to dovetail with the build-up of the ship’s company (Something the RN is increasingly finding harder to manage). Despite being the youngest of the frigates, HMS St Albans has endured the longest time in LIFEX. The work involved 1.2 million man-hours including some 350 structural enhancements, PGMU and the complete removal of her two electric propulsion motors for a major overhaul. Her ship staff moved onboard in November 2023 but she is not expected to be ready for sea until March.
PGMU ambition scaled back
Originally it was intended that 11 of the 13 ships would receive the Power Generation Machinery Upgrade (PGMU) but only HMS Richmond, St Albans and Sutherland will benefit from this. Essentially the upgrade involves replacing the four diesel generator sets with modern equivalents to provide much greater fuel efficiency and performance, especially in hotter climates. (More technical details here). It is unclear if some of the other frigates that have previously completed LIFEX will return to have PGMU at a later date.
The PGMU project presented considerable engineering challenges and attendant costs that were somewhat underestimated at the start. New equipment had to fit within the existing structural and compartment constraints and integrate with the ship’s legacy services and systems. The first frigate to have the PGMU, HMS Richmond went back to sea in March 2020. Her refit employed 350 Babcock staff working a total of 1 million man-hours. 8 km of new cable and 600m of new pipework and were installed. The new diesel-generator sets have to be placed into the Forward Auxiliary Machinery Room (FAMR) below decks. The Upper Auxiliary Machinery Room (UAMR) is on the main deck level and is more easily accessible via deckhead soft patches but was also completely stripped and much equipment re-sited. Richmond has now sailed for thousands of miles and the upgrade has proven to be a success.
Back for more
Following the end of the LIFEX project, ships are now returning for their next upkeep period. HMS Argyll was dry-docked in the Summer of 2022 and is part-way through the project. She was undocked in January but soon after the Daily Telegraph reported HMS Argyll would not be returned to service, essentially due to a lack of sailors with crewing Type 31 and Type 26 being prioritised. However, Babcock say the upkeep is continuing and she is now undergoing ‘post dock-dependent work’. The MoD refuses to confirm that HMS Westminster will be scrapped or comment on plans for HMS Argyll.
Having been run extremely hard since completing LIFEX in 2018, HMS Northumberland will go into the FSC dry dock for a badly needed upkeep period in March. HMS Kent will begin similar maintenance package in June. Under Lloyds certification rules now applied to most RN vessels, ships must be dry docked at least every six years and Babcock will be kept busy with a rolling programme of Type 23 frigate maintenance into the 2030s.
No comments:
Post a Comment
How did you like the post, leave a comment. I would appreciate hearing from you all. Best wishes from JC's Naval, Maritime and Military News