The Bath-built ship, commissioned on 22 June 1991, has been in what would have been described in the old days as “in ordinary” since September 2015 when she shifted homeports from Mayport to Norfolk and entered the CG Mod pipeline.
Gettysburg and sister USS Cowpens started in 2015, followed by USS Vicksburg and USS Chosin in 2016, USS Anzio and USS Cape St. George in 2017, and USS Hue City in 2019.
Each upgrade, originally set for at least 11 cruisers, was set to be accomplished in three phases: tear out, repair, and modernization.
The thing is, it turned out the 25-year-old ships needed a lot more repair than was estimated, particularly with fuel tank issues, hull systems, and piping, then shipyard worker shortages, and finally supply chain issues all dog-piled to stretch the planned multi-month overhaul to multi-year. This was all compounded by the fact that the ships often sat undermanned with just 45 sailor crews for years waiting for the next phase of the program to get started.
“The cruisers right now and the modernization are running 175 to 200 percent above estimated costs, hundreds of days delay. These ships were intended to have a 30-year service life, we’re out to 35,” CNO ADM Mike Gilday told the House Armed Services Committee in 2021.
Speaking of cost, Hue City and Anzio alone were expected to run $1.5 billion each over the course of the CG Mod program, which led the Navy to add them to their “dead pool” of seven cruisers to decommission in FY22. To this was added Vicksburg, even though she was about 85 percent of the way through the CG Mod program meant to extend the life of the ship.
With all that being said, it is nice to see Gettysburg close to being complete. It’s been a long time coming.
No comments:
Post a Comment
How did you like the post, leave a comment. I would appreciate hearing from you all. Best wishes from JC's Naval, Maritime and Military News